Gilbert Road Improvements - Queen Creek Road to Riggs Road 

Project Owner: City of Chandler
Project Type: Construction Manager at Risk
Construction Dates: 12/11 to 04/14

This is a multi-phase, CM@R project for the City of Chandler that began with Gilbert Road Improvements - Germann Road to Queen Creek Road in 2008.

Phase 1 of the Gilbert Road Improvements - Queen Creek Road to Riggs Road project was completed in December 2012. Improvements were made from south of Queen Creek Road to 1,000 LF south of Ocotillo Road and on Ocotillo Road from Norman Way to the east side of Gilbert Road. Those improvements included removals and wet utility improvements (reclaimed water, potable water, sewer adjustments, private irrigation, RWCD irrigation, and a PRV station) as well as surface items: new curb & gutter, paving, sidewalk, concrete bus bays, drainage, SRP overhead to underground conversion, street lighting, City traffic signals at the intersection of Gilbert Road and Ocotillo Road and ITS, landscaping, signing, and striping.

The current phases of Gilbert Road Improvements - Queen Creek Road to Riggs Road include wet utility infrastructure improvements from the previously completed phase south of Ocotillo Road to Riggs Road and roadway improvements to south of Chandler Heights Road.

Wet Utility Infrastructure Improvements: The scope of wet utility services includes installation of jacking and boring at two RWCD piped crossings and one canal crossing, connecting to existing services, vertical realignments to avoid conflicts, installation of valves and hydrants, and relocation of hydrants. In addition to the pipe lines on Gilbert Road, the scope of work also includes installation of a 10” well line on Wood Drive from Gilbert Road to the City’s well site.

9,400 LF 30” DIP water line
8,250 LF 16” DIP water line
6,335 LF 12” DIP reclaimed water line
4,400 LF 10” DIP well water line
2,535 LF 6” to 12” DIP lateral services
2,495 LF 8” and 12” VCP sewer line
33,415 Total LF of pipe

Roadway Improvements: This phase of the project includes roadway widening and new pavement expanding Gilbert Road from a single travel lane in each direction to three travel lanes in each direction, curb & gutter, sidewalk, landscaping and irrigation, undergrounding of the remaining SRP overhead distribution power and Cox communications, relocation of wet and dry utilities, ITS, traffic signals and street lighting, RWCD irrigation, roadway access and utility extensions into the new Taylor Morrison residential subdivision on Chandler Heights Road, regrading and relandscaping the two drainage basins at Brooks Ranch subdivision to meet drainage requirements, permanent and temporary retention basins, and improvements to Chandler Heights Road approximately 0.25 miles to the east and west of Gilbert Road.

Click here to see the PUBLIC OUTREACH WEBSITE for this project

Achen-Gardner-Facebook3  CHECK OUT OUR FACEBOOK PAGE FOR MORE PHOTOS    04-03-13   05-01-13

Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line 

2407101-Gilbert-Road-Imps-290px-380px-2 Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line


Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line



2407101-Gilbert-Road-Imps1-605px-2 Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

2407101-Gilbert-Road-Imps-290px-380px-3 Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

2407101-Gilbert-Road-Imps5-290px Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

2407101-Gilbert-Road-Imps1-290px-3 Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line


2407101-Gilbert-Road-Imps6-290px Achen-Gardner Construction Heavy Civil General Contractor City of Chandler Construction Manager at Risk Project Gilbert Road Improvements new water line

 

Achen-Gardner-Facebook4  LIKE US ON FACEBOOK              Achen-Gardner-Twitter4  FOLLOW US ON TWITTER            Achen-Gardner-YouTube4  WATCH US ON YOUTUBE