Germann Road Improvements

Project Owner: City of Chandler
Project Type: Construction Manager at Risk
Construction Dates: 07/04 to 06/05

The project included reconstruction and realignment for 1.5 miles of Germann Road from Gilbert Road to Airport Boulevard, and the installation of 4.5 miles of 30-inch and 36-inch water transmission main to supply southeast Chandler.  The Germann Road portion of the project consisted of constructing a six lane major arterial. It required new water, storm drain, sanitary sewer, potable water, reclaimed water, and irrigation, utilities, traffic signals, roadway lighting, and landscaping.