Southern Avenue Interceptor Rehab - Phase 2
Project Owner: City of Tempe
Project Type: Construction Manager at Risk
Construction Dates: 03/10 to 03/11
The project included the CIPP rehabilitation of 31,000 LF of 36", 42", and 48" sewer main on Southern Avenue (McClintock Drive to Hardy Drive) and Priest Drive (Broadway Road to University Drive). In addition to the rehabilitation of 50 manholes, bypass pumping, and a jack and bore under the railroad crossing on Southern Ave. and Kyrene Rd., the project included the creation of a diversion structure on Priest Drive north of Broadway Road