Main Street and Lindsay Road Sewer Replacement
Project Owner: City of Mesa
Project Type: Design-Bid-Build
Construction Dates: 08/18 to 11/18
Achen-Gardner constructed sewer system improvements on Main Street from Lindsay Road to Val Vista Road. The scope included the installation of:
212 LF of 16” sewer pipe
2,222 LF of 15” sewer pipe
3,616 LF of 12” sewer pipe
66 LF of 8” sewer pipe
The project also included the rehabilitation of four existing 5’ manholes, the installation of 12 new 5’ manholes, connections to the existing sewer system, and bypass pumping.