Gainey Village Casitas Waterline Replacement CMAR
Project Owner: City of Scottsdale
Project Type: CMAR
Construction Dates: 05/23 to 10/23
We installed more than 5,000 linear feet of new 6”- 8” DIP waterline, 30 valves, 179 water service connections, five air release valves, and 15 cathodic protection test stations with anodes. We also relocated six fire hydrants and installed four new fire hydrants. All this work was done within the Gainey Village Community in North Scottsdale. We coordinated with the homeowner’s association and residents in the community to maintain access and minimize disruptions.