Detroit Basin/Gazelle Meadows Park Storm System and Associated Improvements
Project Owner: City of Chandler
Project Type: Construction Manager at Risk
Construction Dates: 11/23 to 05/25
This project will address flooding issues by improving drainage in the area of Detroit Basin and Gazelle Meadows Park, and provide other much-needed improvements to water and sewer infrastructure in the surrounding neighborhood. It will include:
34 manholes
36 catch basins
7,113 LF of ADS storm drain (12” to 36”)
1,042 LF of VCP sewer (8”)
308 LF of CIPP (8”)
1,905 LF of waterlines with valves and fittings (1”, 6”, and 12”)
Replacement of concrete and asphalt
We are installing more than 7,000 LF of large diameter storm drain, 36 catch basins, and 34 manholes in a residential area of Detroit Basin and Gazelle Meadows Park. This neighborhood has had flooding issues for years and we are proud to be working with the City of Chandler and Entellus (design engineer) to improve storm drain conditions as well as other, much-needed water and sewer infrastructure. We are working with residents and stakeholders to maintain safety and access during construction.