16-inch Water Line in Verrado between Van Buren and Yuma Road with Pressure Release Valve and EPCOR Water Line Interconnect at Dean and McDowell
Project Owner: City of Buckeye
Project Type: Construction Manager at Risk
Construction Dates: 03/23 to 11/23
Project Description: We recently completed phase one of this project which included installing 5,400 LF of 16-inch water line on Verrado Way just north of Yuma Road in the City of Buckeye. We also completed three jack and bores under box culverts totaling 150 feet and installed a PRV on the line as well. The second phase includes more than 2,600 LF of 12-inch DIP and has been completed in an area of future development.