This job order contract was for emergency repair services on wet utilities throughout the City of Mesa. These emergency repair services included water, sewer, and irrigation lines throughout the City of Mesa. We completed four repairs, including:
Carbon unit installation at the Lehi Lift Station.
Assessment and removal of a 24” water valve and installation of five feet of 24" diameter water line.
Repair 8” CCP, removal of the old mortar coating, and restoration of the mortar lining.
Repair of a water main break at Gilbert Road and Southern Avenue. Our team received a call on a Friday and began work within an hour. We worked with the City of Mesa to perform work 24/7 across five days. This water main break hindered access to a bus station, which amplified the urgency to restore usability of the road.